What is a Sprint Retrospective?
Answer
The Sprint Retrospective is a time-boxed event (max 3 hours for 1-month Sprint) held after the Sprint Review and before the next Sprint Planning. Its purpose is for the Scrum Team to plan ways to increase quality and effectiveness. The team inspects: how the last Sprint went (individuals, interactions, processes, tools, DoD); what went well; what problems occurred; how problems were solved. The outcome: identifies the most helpful changes and adds them as improvements to the next Sprint. The Retrospective is the team's opportunity for continuous improvement — a structured reflection ritual. Common formats: Start/Stop/Continue, Mad/Sad/Glad, 4Ls (Liked, Learned, Lacked, Longed For), Prime Directive reminder ("Everyone did the best job they could given the circumstances"), and dot voting on action items. At least one high-priority improvement should become a Sprint Backlog item in the next Sprint.